Construction work in 2026: Closures on B103, A24 and district roads are imminent!

Transparenz: Redaktionell erstellt und geprüft.
Veröffentlicht am

In 2026, Prignitz is planning extensive construction work on roads with numerous closures. Find out more about the details and implications.

Im Jahr 2026 plant die Prignitz umfassende Bauarbeiten an Straßen mit zahlreichen Sperrungen. Erfahren Sie mehr über die Details und Auswirkungen.
In 2026, Prignitz is planning extensive construction work on roads with numerous closures. Find out more about the details and implications.

Construction work in 2026: Closures on B103, A24 and district roads are imminent!

There will be extensive construction sites in Prignitz in 2026 that will affect both traffic and the region's infrastructure. Loud maz online The largest interventions are planned on the B103, A24 and several district roads. For residents, this not only means possible traffic restrictions, but also an improvement in the traffic infrastructure.

Specifically, the B103 is involved in several construction phases, with work continuing between the L155 state road and Meyenburg and between Gantikow and Vehlow. The roadways will be renewed and cycle paths will be created. The work should be completed by the end of 2026 and enable new, modern transport connections.

The current status of theB103 in the Gantikow area, which is almost finished. From December 22, 2025, the connection to Kyritz via the B103 can be used again, which is a relief for residents. Nevertheless, the route between Gantikow and Vehlow will remain fully closed until January 11, 2026 in order to complete the remaining work. This renovation includes, among other things, the renewal of the roadway and the improvement of drainage by installing trenches such as the Brandenburg state government reported.

Renovation costs and measures

The A24, which has been renovated between Meyenburg and Pritzwalk in the direction of Hamburg since September 2025, also brings changes. Here, 7.8 kilometers of the roadway are affected, and with investments of around 15.7 million euros, the work is expected to last until April 2026.

But it's not just the federal highways that are in focus. The Prignitz district is also planning four measures on district roads with a total cost of around 5.6 million euros, a large part of which will be covered by funding. This work affects a total of 6,510 meters of road, but there is currently no exact date as the funding notices are still pending.

  • K7041 in Berge: Ortsdurchfahrt wird auf 6,50 Meter verbreitert. Kosten: 565.050 Euro.
  • K7005 zwischen Abzweig K7006 und Roddan: Fahrbahn wird auf sechs Meter verbreitert. Kosten: 1.413.750 Euro.
  • K7020 von Schmolde zur L14: Straße soll auf fünf bis sechs Meter verbreitert werden. Kosten: 2.316.500 Euro.
  • K7009 zwischen B103 und Dannenwalde: Verbreiterung der Fahrbahn auf sechs Meter. Kosten: 1.327.300 Euro.

Background and outlook

The infrastructural challenges in road construction are noticeable nationwide and throughout Germany. The condition of many roads is deteriorating, partly due to insufficient investment in the past. The federal government has already put together a restructuring package worth around 500 billion euros to counteract the situation. In 2024, a turnover of over 14 billion euros was recorded in road construction and more than 80,000 people are employed in this sector, but many citizens are dissatisfied with the condition of roads, such as Statista shows.

Overall, the citizens of Prignitz can hope for a significant improvement in their transport connections, even if they have to be patient during the construction work. The high investment needs and the numerous measures demonstrate a clear plan to improve the transport infrastructure, which is essential for the development of the region.